Some of the success parameters

A reduction of 60% in rig up and down (D50) times. This equals 2,4 days per well, and a total of 10 days saved for 4 wells!

Reducing the amont of lifts required with 18 lifts per well

No scaffolding required! Improving health and safety (HSE) – reducing risk and exposure for work-at-height (WAH) and dropped-objects (DROPS)

Elimination of guy-wires freeing up deck space

We are very satisfied, Shell Wells globally get a lot of interest from all around the world. Shell UK, Brent C plattform